How long does it take to install a GRP Roof
Just wanted to know how long it would take to lay a fibreglass roof, we have a 15 square metre garage roof that needs to be done and we are getting roofers quoting us 3 days to complete the job.

A typical GRP roof installation of up to 20 square metres can be installed by a team of two contractors within a day. This would involve stripping the existing roof, laying fresh decking and applying the new system.
The weather is one of the main problems for holding up a GRP roofing job but a professional contractor would always prepare for that scenario and plan an installation around a block of good weather.
The amount of time you have been quoted there seems a bit excessive for the square metres you have to cover and would recommend you get a second opinion either from us or another GRP roofing contractor.

Related questions
Here are some more questions you may find helpful.
Green roof guard trim
Do I need to use the guard trim on my green roof?
Can I cut the green roofing modules?
Can I cut the green roofing modules down to size?
Resin coverage
How much will a single can of GRP fibreglass roofing resin cover?